TRAFFIC ALERT: Next phase of “Off Broadway” construction project set to begin Monday

I-235 and I-44 in Oklahoma City

This is an archived article and the information in the article may be outdated. Please look at the time stamp on the story to see when it was last updated.

OKLAHOMA CITY – The next phase of a construction project along I-235 in Oklahoma City is set to begin Monday.

The two-year project will primarily impact northbound and southbound I-235 between N. 50th St. and N. 63rd St.; however, the Oklahoma Department of Transportation says the interstate will remain open to two lanes of traffic in each direction majority of the time.

“It’s probably going to be the most disruptive [phase] because we normally work from the outside of an interchange and work our way into the interchange, so this is going to be right in the heart in the interchange over I-44 on I-235 where two major interstates intersect,” Terri Angier with ODOT said. “Each of these interstates carry over about 100,000 cars a day so it’s a major, major project for us.”

During this next phase, the project includes 11 new bridges with two flyover bridges that will allow traffic to flow more efficiently from NB I-235 to WB I-44 and from EB I-44 to NB I-235.

Data pix.

ODOT is encouraging drivers to start planning now for the following traffic impacts later in the project:

  • Up to four full weekend closures of I-235 to remove and hang bridge beams;
  • One weekend closure of I-44 for bridge beams;
  • A nearly two-month closure of the northbound I-235 off-ramp to N. 63rd St.;
  • Closure of the northbound I-235 off-ramp to N. 50th St. to complete the ramp widening;
  • Intermittent lane closures of N. 50th St. and Santa Fe Ave. for intersection modification; and
  • An up to two week closure of the southbound I-235/US-77 off-ramp to eastbound I-44 and the westbound I-44 on-ramp to southbound I-235 while these two clover leaf ramps are widened and improved.

The seventh phase is going to cost about $105 million, according to ODOT. In project in total, represents a nearly $300 million investment in highway infrastructure.

Once it is done, there is another piece of work crews will start on.

"What it will do is connect Lincoln Boulevard directly to northbound Broadway Extension," Angier said. "Right now, the only way is to get on I-44 and make a couple of jogs before you can get to Broadway extension north."

ODOT is recommending drivers stay off Broadway during the construction and use alternative routes including I-35, SH-74/Lake Hefner Parkway, I-44, I-40 and Lincoln Blvd.

For more information about the project, click here.

Local

More Local

National News

More National

Washington D.C.

More Washington DC Bureau

In Your Corner

More In Your Corner

Your Local Election HQ

More Your Local Election HQ

Latest News

More News

Popular

KFOR Podcasts

More Podcasts

Follow @KFOR on Twitter